July 9, 2021

Per the look-ahead schedule on this page, the water line will be placed in the next couple weeks. The water line will be placed in a trench, and the Contractor will have to cross the Tacoma Country Club (TCC) driveway. New water stubs will be placed perpendicular to the water line, and many of those stubs cross the entire length …

May 26, 2021

Construction is anticipated to begin starting the week of June 1, 2021. The North-bound, right lane of Gravelly Lake Dr., as well as the turning (slip) lane – will be closed permanently. These closures will occur for a minimum of two (2) weeks in order to prepare for the upcoming complete closure of Gravelly Lake Dr. Please see the image …

May 13, 2021 Update

A pre-construction meeting was held on May 13, 2021 with City of Lakewood personnel, the General Contractor and various utility companies. The General Contractor informed all present that the start date requested is Tuesday, June 1, 2021. The work performed is described in the April 22, 2021 Update for the JBLM North Access Road Improvements. Although road closures are not …