Stormwater infrastructure installation along Washington has been slowed by conflicting underground utilities. The contractor is working diligently to get the new drainage completed so that they can start the water main and other underground infrastructure. Once utilities are complete, they will grade, pour the concrete roundabout and curbing, and pave the sections currently graveled between North Gate/Nottingham and Washington/Vernon.

Concrete pavement at North Gate Road and Edgewood Avenue will be poured on September 12 and September 19. Crews are starting to prepare landscaping in this area.