August 23, 2021

Water main construction has been completed from Nyanza to Veterans Drive. This week, the contractor will begin testing the main and connecting homes along the stretch to the new main. Concrete curb and gutter are poured from Nyanza to Country Club Drive. This week, the contractor will extend the curb to North Street. They will then set back and start …

August 9, 2021

The project is progressing on schedule. Curbing for the new roundabout at Nyanza has been poured. The water main extension will approach Veterans Drive by the end of the week. Storm drainage is progressing just behind the water main work. Once the utilities are completed, the contractor will commence grading in preparation for curb pours. Asphalt base for the first …

June 29, 2021

The extended road closure of Gravelly Lake Drive was put into place on Monday, June 28. The contractor has removed the traffic signal at the south end of Nyanza and is removing the pavement in the intersection and will be heading toward Veterans Drive. Water main and storm drainage improvements will be completed along Gravelly toward Veterans within the next …

June 8, 2021

Starting June 9, the contractor will close Nyanza Road in the northbound direction from the Gravelly Lake Drive intersection in order to connect the new water main to the existing main. The closure detour is shown above. Once the water main is complete and tested, the contractor will prepare the bypass lane in preparation for the main closure of Gravelly …

April 22, 2021 Update

The start of construction is currently being delayed due to material availability. The City will ensure that the contractor has all the material ready for the crews to start and complete the work without suspension, as the City acknowledges the impact that the detour will have on every individual traveling around the lake, as well as those living in the …