Project Description: This project, which is 0.80 miles, will provide an asphalt overlay and upgrade existing curb ramps to meet current ADA standards as required for all overlay projects.
Estimated Cost: $746,000
Project Manager: D’Andra Buchanan, 253-983-7820.
Project Status: This project has been awarded to Northwest Cascade, Inc. of Puyallup, WA.
Construction began on April 19, 2021.
Construction was completed on July 28, 2021.
Before and After Photos
Before: Looking west on 108th, just west of Pacific Highway
After: Looking west on 108th, just west of Pacific Highway
Before: Rowland Ave SW and 108th Intersection
After: Rowland Ave SW and 108th Intersection
Before: Looking west at the Railroad Tracks before Lakeview Ave SW
After: Looking west at the Railroad Tracks before Lakeview Ave SW
Before: Looking west at 47th Ave. SW and 108th intersection
After: Looking west at 47th Ave SW and 108th intersection
Construction Photos
Existing concrete sidewalk is being removed from the north-west corner of 108th St. SW and Freiday St. SW.
The backhoe placed the existing concrete slab aside to prepare for the new ramp and sidewalk.
Crews work on fixing a storm drain pipe along 108th St. SW before the overlay.
Concrete forms are being placed in the north-west corner of 108th and Addison.
Concrete comes out of a concrete truck at the north-east corner of 108th St. SW and 47th.
After the concrete pour at the north-east corner of 108th St. SW and 47th St, a sidewalk closed ahead sign is placed for the concrete to cure prior to usage.
The valves and manholes must be lowered in order to pave the road. They will be raised after the paving portion of the roadway is complete.
Near the intersection of 108th and Cronis, the grinding machine is grinding existing asphalt that is too damaged to pave directly over.
The milling machine is removing material along 108th near the railroad tracks in the west bound lane.
At the match point near Pacific Highway, the road has been ground down so that paving can be matched to the existing roadway when the new overlay gets placed.
The paving machine is turning the corner of Addison at 108th St. A roller in the background rolls the asphalt after placement.
The roller makes passes over the newly placed asphalt along 108th.
Heat evaporation is visible as one of the paving machines lays asphalt at the intersection of Freiday and 108th.
A striping crew member prepares the roadway for the new striping
A crew member walks along-side the truck as it places yellow MMA permanent striping.
As the work was done at night, a crew member continues to walk along the striping truck for the second lane line.
The lane lines for the turn pocket along 108th have been placed.
A striping crew member looks at the newly placed turn arrow.
The striping truck places the bike lane stripe along 108th.