The project is progressing on schedule. Curbing for the new roundabout at Nyanza has been poured. The water main extension will approach Veterans Drive by the end of the week. Storm drainage is progressing just behind the water main work. Once the utilities are completed, the contractor will commence grading in preparation for curb pours. Asphalt base for the first stage is tentatively scheduled for early October.