Water main construction has been completed from Nyanza to Veterans Drive. This week, the contractor will begin testing the main and connecting homes along the stretch to the new main.
Concrete curb and gutter are poured from Nyanza to Country Club Drive. This week, the contractor will extend the curb to North Street. They will then set back and start pouring sidewalk and roadway panels in the Nyanza roundabout.