Image that says "Capital Projects" over a picture of construction.

Capital Projects

The Capital Projects division oversees all road improvement projects in the city. This is where you can learn about current projects, construction updates and what projects are coming up.

Language

Español
Korean
Tagalog
English

Project Map

Download PDF version

Total anticipated investment in Lakewood roads, pedestrian access and infrastructure in 2026: $25.725 million

  • Kendrick Street – 111th to 108th ($1.75 million)*
  • 112th Street – Gravelly Lake to Bridgeport ($3.5 million)*
  • Nyanza Road ($4.3 million)**
  • Mt Tacoma Drive – Interlaaken to Whitman ($4.3 million)**
  • 2026 Chip Seal Program ($400,000)***
  • 2025 Pavement Patching Program ($175,000)***
  • 2023/24 Street Light Program ($350,000)***
  • South Tacoma Way/92nd Street signal ($750,000)****
  • 112th Street – S Tacoma Way to Steele overlay ($1.2 million)****
  • Custer Road – Bridgeport to 75th ($3.5 million)****
  • Grant/Orchard sewer installation ($1.8 million)****
  • Silcox/Wadsworth/Boat sewer installation ($2.4 million)****
  • 112th Street – Farwest to Holden ($1.3 million)****

* Funded from Lakewood Station Access Improvement Project totaling $5.25 million.

**Funded from Transportation Benefit District collections and other city/grant funds totaling $8.6 million.

***Annual street maintenance/lighting totaling $925,000.

****Project is funded through grants ($7.2 million) and City Funds ($3.75 million) totaling $10.95 million


Active Projects

Custer Road – Bridgeport to 75th

Update 10/22/26-11/2/26. Custer Road is fully open. Remaining work includes standing streetlight poles and wiring once all the material arrives. Minor lane closures which should not significantly impact traffic will be required to stand the poles.

The total project is estimated at about $2.74 million funded by a grant from the Transportation Improvement Board. This project will construct a two-way left turn lane, sidewalks, curbs, storm drainage, street lighting and a reconstructed roadway.

Find detailed project information at https://cityoflakewood.us/custer-road/

Kendrick Street – 111th to 108th & 111th Street- Bridgeport to 112th Street

Update 10/22/26-11/2/26. Bids were received and opened on October 21. Lakewood received competitive bids under the engineer’s estimate and budget. Following review of the bids, award is anticipated to be forwarded to City Council for their consideration on Monday, November 2. Construction is anticipated to start in December or January.

This project will construct a green street concept with new pavement, curbs, bike lanes, sidewalks, planters, street lights, storm drainage, and water main replacement along Kendrick between 111th to 108th Street. 111th Street will have similar improvements, but will not have street lighting.

Questions? Contact Design Engineer Eric Swanstrom at 253-983-7751 or email [email protected]

Silcox, Wadsworth, and Boat Sewer Extension

Construction Update 10/22/26-10/28/26: Curb and sidewalk are anticipated to be poured in a few locations on Monday, October 26. Crews will pave a few more driveways and finish final cleanup next week before demobilizing.

The Lakewood City Council approved a construction contract in 2025 for a sewer main extension along Silcox Avenue, Wadsworth Avenue and Boat Street. Total project cost is estimated at $1.9 million.

Improvements include:

  • Sewer Main Extension
  • Replaced asphalt roadway
  • Replacement of sidewalk panels where the sewer service lines require removal of existing sidewalk

Questions? Contact Civil Engineer JB Hur at 253-983-7845 or [email protected]


Recently Completed Projects

These pedestrian safety and infrastructure improvement projects were recently completed across the city:

112th Street – Farwest to Holden

This project added sidewalks, curb and gutter, and bike lanes to 112th Street between Farwest and Holden. The contractor still needs stripe the roadway and install street lighting. Those activities will be coming in the following weeks.

112th Street – Gravelly to Bridgeport

The total project is estimated at about $3.5 million funded entirely from the Sound Transit Lakewood Station Access Improvement project. This project constructed sidewalks, bike lanes, storm drainage, street lighting and a reconstructed roadway.

Nyanza Road

In the spring 2025 the Lakewood City Council approved a construction contract to make road safety improvements to Nyanza Road SW. Total project cost is $4.3 million.

Improvements included:

  • Curb and gutter
  • Sidewalks
  • Stormwater infrastructure, replacing old systems to improve water quality of stormwater runoff
  • Asphalt paving
  • Concrete pole streetlights
  • New Lakewood Water District water main (collaborative project with LWD)

112th Street – S Tacoma to Steele

This project overlaid 112th Street from S Tacoma Way to Steele Street. Improvements included new pavement, pavement striping, and traffic signal modifications.


Documents

All links below lead to a PDF document


Contact

Operations & Maintenance (24/7)
Report an issue via 311 or call 253-267-1628

back to top